A time-of-use tariff is an electricity rate schedule in which the price per kilowatt-hour depends on the time block in which the energy is consumed — a higher peak price inside a defined daily window, a lower off-peak price outside it, and often a shoulder price between the two. The windows are written into a published schedule, and the meter has to record when energy was used, not only how much.

Most explanations stop there. The useful part is one level down: the schedule is a stack of a network charge, a retail charge and a market price, each recovering a different cost, each moved by a different party on its own timetable. A battery sells into one layer at a time, and that layer decides whether the project survives the next re-filing.

What a Time-of-Use Tariff Actually Prices

What is being priced is not electricity in general but capacity at a particular hour. A distribution network is built for its worst afternoon and sits mostly idle the rest of the year, so the schedule makes idle hours cheap, pulling consumption toward them.

Two boundaries matter. A time-of-use tariff is not a demand charge: it prices energy in kilowatt-hours by block, while a demand charge prices the highest rate of draw in kilowatts over a billing interval, whenever the energy inside it was used. Nor is it real-time pricing: a block rate is published in advance and holds for a season or a year, while dynamic products follow the wholesale market at settlement intervals. A flat rate, by contrast, charges one price whatever the hour.

Both share one prerequisite — interval measurement. Without a meter recording half-hourly or hourly consumption no block rate applies, which is why the tariff and the smart-meter rollout travel together.

The boundaries are also hard edges, not ramps. A load finishing at 3:58 pm and an identical one finishing at 4:02 pm land in different blocks and are billed differently. That is what makes storage a candidate: a machine can move energy across an edge to the minute; a production schedule usually cannot.

Who Sets the Numbers: Three Layers, Three Clocks

The same kilowatt-hour can carry three prices at once; the first question of any schedule is which one it quotes.

Start with the network layer: the poles and wires. A distribution business sets windows reflecting when its assets are under strain, files them, and recovers cost through a use-of-system charge. Regulating a physical constraint, the windows follow network peaks, not customer convenience.

The retail layer is the supply contract. A retailer buys energy, adds cost and margin, and decides how much of the network shape to pass through. The divergence is stated plainly on at least one network's own page: the periods that apply to a customer depend on the retailer, which "may choose to apply different peak and off-peak times and charges" (Ausgrid).

The market layer is the wholesale price underneath both, long invisible behind the tariff and now becoming a product in its own right: under Article 11 of Directive (EU) 2019/944, member states must let suppliers offer dynamic electricity price contracts, and a customer with a smart meter can request one from at least one supplier.

For a United States site the filed schedules are public — the OpenEI Utility Rate Database holds rate-structure information for over 3,700 utilities. That document is the one to read; a retailer's page is a summary, sometimes of an older version.

Metering and switchgear cabinets where the network measurement meets retail pricing

Layer

Who sets it

What it recovers

How fast it moves

Network / distribution

Distribution business, approved by the regulator

Poles, wires, substation capacity

Slowly, on a published tariff cycle

Retail supply

Energy retailer

Energy cost, hedging, margin

Each contract renewal

Wholesale market

Market clearing

Marginal cost of generation

Half-hourly, where exposed

That is why neighbouring sites with identical load shapes can pay different amounts for the same block, and why a case built on one layer's numbers fails quietly when another moves.

Reading the Block Structure: Seasons, Weekends and Hard Edges

A block schedule has four variables, and most summaries of "peak and off-peak times" report one of them.

First, which hours fall in which block. Second, which days — weekday, weekend and holiday prices often differ. Third, seasonal redefinition: the boundaries move. Ontario's regulator runs different periods from 1 May–31 October and 1 November–30 April, with on-peak hours mid-day in summer when air conditioning drives the peak, and two windows in winter when demand peaks before and after work (Ontario Energy Board).

Fourth, some months may have no peak at all. One Australian network applies peak pricing from 3 pm to 9 pm in June–August and November–March, and charges no peak rate in April, May, September or October. A model assuming twelve peak months overstates a battery's value by a wide margin.

Some schedules add critical peak events: individual days, called a day ahead, when the peak price multiplies for a few hours. They reward reserve held for short notice, not a fixed daily cycle.

The output here is a number, not a sentence: for each season, count the hours in each block, count the days, multiply. "Peak is 4 to 9 pm" is not a sizing input; a yearly hour count is.

Where the Spread Becomes a Storage Case

Arbitrage is the price gap between the cheap block and the expensive one, captured by moving energy across the boundary.

Value per cycle is the spread × energy moved × round-trip efficiency. Annual value is that × the cycles the schedule offers, minus degradation and auxiliaries.

An illustrative case, numbers chosen for arithmetic not any market: a spread of $0.10/kWh, 500 kWh usable, 88% round-trip efficiency, 300 cycles a year inside the blocks — $0.10 × 500 × 0.88 × 300 ≈ $13,200 a year, before capacity fade and cooling load.

Three terms in that sum are where projects fail. Round-trip efficiency is a direct multiplier, so a system quoted at 88% returns 12% less than the spread suggests, every cycle (round-trip efficiency is an economic number before it is a datasheet line). Usable energy is smaller than nameplate: depth-of-discharge limits and the state-of-charge band held back for warranty and backup reduce what can be cycled — and holding it back is usually right, since a system emptied for arbitrage has nothing left when the site needs it. Auxiliary load is easy to forget: thermal management runs hardest in the hot afternoons that carry the peak price, so part of the revenue cools the asset that earns it.

Battery cabinets and inverters in an industrial plant room holding cheap off-peak energy

The Second Clock: Demand Charges on the Same Bill

For a commercial or industrial site the bill carries two lines: energy in kilowatt-hours, and demand in kilowatts. How the total splits between them depends on the site's load factor — a three-shift plant can sit most of its bill in the energy line, a single-shift site can approach an even split — which is why the two are sized separately.

A demand charge is "that portion of the consumer's bill for electric service based on the consumer's maximum electric capacity usage", per the EIA's definition. It is measured over an interval of 15, 30 or 60 minutes and charged on the highest in the billing period, not the average.

That produces the field's most common sizing error: assuming one battery serves both clocks on one dispatch. Arbitrage wants to charge cheap and discharge expensive — a daily energy problem. Demand response wants to clip the month's highest peaks, which may be three afternoons, none in the peak block, each needing a shallower, faster discharge.

One system can serve both, but the objective has to be ordered before capacity is chosen: sized for the peak block it is under-muscled for a demand spike, and sized for the spike it is oversized for arbitrage and cycles less than the case assumed. Peak shaving covers the second objective in its own right, and a demand-charge calculator shows quickly whether the kW line or the kWh line dominates a site.

A substation transformer and gantry at an industrial site, where capacity constraints sit

Reading a Schedule Before You Size Anything

Five checks, in order, before any capacity number is fixed.

Get the filed schedule. Not a retailer's summary or a comparison table, but the current rate document for that meter and voltage level. A table copied last year may describe a product that no longer exists.

Pull twelve months of interval data. The schedule says when energy is cheap; the data says when the site consumes it, which decides how much can shift without touching production.

Convert the schedule into hours. Hours per block, per season, per year, and the cycles those hours physically allow. That sets the ceiling on annual value, not the headline spread.

Check the export treatment. A block rate governs imported energy; energy pushed back to the grid follows a separate rule, sometimes a supplier obligation rather than a tariff — under the UK's Smart Export Guarantee, suppliers with at least 150,000 domestic customers must offer a SEG tariff to small-scale low-carbon generators for exported electricity, and smaller suppliers may opt in. Exporting at the wrong moment can be worth less than storing and using later — and the reverse holds on sites with a large midday solar surplus.

Read the contract around the schedule. Ratchets, minimum billing demand and notice periods can outlast the price signal that justified the project.

None of this is a spreadsheet exercise. It turns a rate schedule into a dispatch specification, and that specification is what an energy management system executes: an EMS given the block structure and a load forecast holds a system in the cheap hours far more precisely than a fixed time-of-day timer.

Rooftop solar on a factory roof with two grey battery cabinets on a concrete pad below

The Tariff Can Be Repriced Under You

Every number above is a policy decision, and policy decisions move.

Time-based pricing is spreading. Lawrence Berkeley National Laboratory's 2024 retail price and cost trends report records residential enrolment in time-based pricing, including time-of-use and critical peak pricing, up almost 80% between 2019 and 2023; commercial enrolment more than 20% higher in 2023 than 2019; and in 2023 over 10% of residential and over 11% of commercial and industrial customers on time-varying rates nationwide (LBNL, 2024). Several jurisdictions went further and made the tariff the default — California in 2019, Xcel Energy in Colorado in 2022, Michigan in 2023 — with customers able to opt out.

Default enrolment and dynamic contracts are two directions of one reform; both compress a naive arbitrage case. If enough load leaves the peak window, the peak moves and the regulator re-files the schedule around it. A system designed against a static 4-to-9 pm window can end up charging in a block that is no longer cheap.

The design consequence is unglamorous: keep dispatch configurable, keep control separate from hardware, and do not underwrite a fifteen-year asset against a spread a regulator can re-file in eighteen months. Size for the site's energy and power; treat arbitrage revenue as what gets re-checked, not what is guaranteed.

How Hua Power Approaches a TOU Site

The method above is close to how the application work is done: start with the tariff and peak shape, then choose power and energy. Picking kW and kWh first and hunting for a rate to justify them afterwards is how systems end up cycling less than their case assumed.

Hua Power builds commercial and industrial storage and residential systems, with an energy management layer that can be configured against tariff blocks, load forecasts and on-site solar. The question at the start is not which product, but which block on which schedule is being sold into — and whether that block will exist in five years.